Wind Power Converter 2.5 MW — Enclosure & System Design

Full-power converter enclosure for 2.5 MW onshore wind turbines — from mechanical concept to series-ready design. Installed in the turbine tower base.

2.5 MW Wind Power Converter — concept design pilz

Sector
Power Electronics / Renewable Energy

Product
Full-power converter enclosure · 2.5 MW · 690 V · Onshore

Scope
Mechanical design, cooling system, busbar routing, documentation

Period
2012 – 2014

The task

A 2.5 MW full-power converter for onshore wind turbines requires an enclosure that is robust under harsh conditions, service-friendly in confined tower spaces, and thermally optimised for continuous high-power operation. The design had to accommodate a complete water cooling system, a DC/AC copper busbar network, and a plug-in rack system — all within a welded steel frame.

Our contribution

Complete 3D mechanical design in SolidWorks — from concept to production-ready documentation:

Welded steel frame with plug-in rack system (60+ assemblies)

Water cooling system — cooling plates, manifold pipes, hydraulic brackets, seal frames

Copper busbar network DC / grid / PE

Reactor mounting, drawing set + BOM Rev.06, test & acceptance specification

Wind Power Converter Steel Frame — concept design pilz

The result

A series-ready full-power converter enclosure for 2.5 MW onshore wind turbines — complete with 3D model, 2D drawings, BOM, and test & acceptance specification.